What Should Be Checked During Transformer Factory Inspection?

November 06, 2026

Share:

Before a transformer is delivered to a project site, factory inspection plays an important role in verifying its manufacturing quality and compliance with approved technical specifications.

Whether it is a dry-type transformer or an oil-immersed transformer, a systematic factory inspection helps identify potential manufacturing defects, confirm that the product meets project requirements, and reduce potential problems during installation and commissioning.

So, what should be checked during transformer factory inspection? The following points provide a practical overview.

1. Appearance and Structural Inspection

The first step is to check the overall appearance and mechanical structure of the transformer.

Important inspection points include:

Tank and enclosure: Check for deformation, damage, corrosion, and paint defects.

Welds and mechanical connections: Inspect visible welds, flanges, and mechanical connections.

Bushings and terminals: Check for cracks, damage, and proper installation.

Accessories: Verify that cooling fans, temperature indicators, pressure relief devices, and other accessories are correctly installed according to the approved design.

Nameplate: Confirm that the nameplate is securely attached and clearly marked.

For dry-type transformers, additional attention should be paid to the condition of cast resin or VPI insulation systems, winding surfaces, insulation components, ventilation ducts, and protective enclosures.

2. Verification of Technical Parameters

All transformer parameters should be checked against the approved technical specifications, drawings, and purchase requirements.

Key parameters include:

Rated capacity (kVA)

Primary and secondary voltage (kV)

Rated frequency (Hz)

Number of phases

Vector group

Impedance voltage (%)

Winding material

Insulation class

Cooling method

Tap changer range

For oil-immersed transformers, inspectors should also verify the oil level, sealing condition, conservator, and cooling system, where applicable.

For dry-type transformers, the inspection should include the winding insulation system, temperature monitoring devices, and enclosure protection rating.

3. Inspection of Main Components and Accessories

The quality and installation of major components directly affect transformer performance and reliability.

Depending on the transformer design, the following items should be inspected:

ComponentsInspection Points
Core and windingsAssembly condition and visible defects
BushingsType, rating, and installation
Tap changerPosition, operation, and connections
Cooling systemFans, radiators, and airflow
Temperature controllerInstallation and function
Protection devicesInstallation and operation
Transformer oilOil level and relevant quality test results

The actual inspection scope depends on the transformer type, design, and project requirements.

4. Electrical Tests and Performance Verification

Electrical testing is one of the most important parts of transformer factory inspection. It helps verify whether the transformer meets the specified electrical and insulation requirements.

According to IEC 60076 and applicable project specifications, routine tests generally include:

Measurement of winding resistance

Measurement of voltage ratio and check of phase displacement

Measurement of short-circuit impedance and load loss

Measurement of no-load loss and current

Separate-source AC withstand voltage test

Induced AC withstand voltage test

Additional tests may be required depending on the transformer design and contractual requirements.

For example, temperature-rise tests, lightning impulse tests, and sound-level measurements are generally classified as type tests or special tests rather than standard routine tests.

5. Inspection of Technical Documents

In addition to physical inspection and electrical testing, relevant technical documents should be reviewed before shipment.

These documents may include:

Approved technical drawings

Transformer nameplate data

Routine test reports

Material and component certificates, where required

Transformer oil test reports, where specified

Operation and maintenance manuals

Inspection and quality records

All documents should be consistent with the actual product and the approved project specifications.

6. Final Inspection Before Delivery

After completing the inspection and testing procedures, a final check should be carried out before the transformer leaves the factory.

The final inspection generally includes:

Confirming that all required inspections and tests have been completed.

Checking that accessories and spare parts are included.

Verifying that the transformer is properly cleaned and prepared for transportation.

Checking protective packaging and transportation arrangements.

Confirming that all required documents are available.

Proper packaging and transportation preparation help reduce the risk of mechanical damage during delivery.

Conclusion

Transformer factory inspection is an important step in verifying that a product meets its technical and quality requirements before shipment. From appearance and component checks to electrical testing and document verification, each stage contributes to the overall quality control process.